WCE (West Coast Expressway): E32
Long time awaited coastal highway is finally here. Partially opened since 19/May/2019 onwards.
Let's wait for its 100% completion.
It will definitely be beneficial to my hometown Sitiawan, one of the speediest development areas in Perak.
Update [@2019-12-20]:
[2021/Q1 ] Section 01/02/03: Banting - Federal Highway 2
[2020/Q1 ] Section 04: Federal Highway 2 - Bandar Bukit Raja (North)
[2019/12/10] Section 05: NNKSB (Shahpadu Highway) - Bandar Bukit Raja (North) were opened
[2021/Q1 ] Section 06: Kapar - Assam Jawa
[2024/?? ] Section 07: Assam Jawa - Tanjung Karang
[2019/05/31] Section 08: Hutan Melintang to Teluk Intan were opened
[2019-09/23] Section 09/10: Kampung Lekir - Beruas were opened
[2022/Q4? ] Section 11/12: Beruas - Changkat Jering
Update [@2022-12-20]:
[2022-12-22] Teluk Intan / Hutan Melintang Bridge (Jambatan Sultan Yusof) open to public
Update [@2023-11-20]:
[2023/11/21] Section 06: Kapar - Assam Jawa open to public
Update [@2024-03-12]:
[2024/03/12] Section 11/12: Beruas - Changkat Jering. Free for 2 months.
Update [@2024-08-28]:
[2024/08/30] Section 01: Banting - SKVE
[2025/Q3? ] Section 02: SKVE - KESAS
[2024/12/31] Section 03: KESAS - Federal Highway Route 2
[2024/12/31] Section 04: Federal Highway Route 2 - Bandar Bukit Raja (North)
[2019/12/10] Section 05: NNKSB (Shahpadu Highway) - Bandar Bukit Raja (North)
[2023/11/21] Section 06: Kapar - Assam Jawa
[2024/Q4? ] Section 07: Assam Jawa - Tanjung Karang
[2019/05/31] Section 08: Hutan Melintang - Teluk Intan
[2019/09/23] Section 09/10: Kampung Lekir - Beruas
[2024/03/12] Section 11/12: Beruas - Changkat Jering
Update [@2025-02-03]:
[2024/08/30] Section 01: Banting - SKVE
[2025/01/22] Section 02: SKVE - KESAS
[2025/? ] Section 03: KESAS - Federal Highway Route 2
[2025/? ] Section 04: Federal Highway Route 2 - Bandar Bukit Raja (North)
[2019/12/10] Section 05: NNKSB (Shahpadu Highway) - Bandar Bukit Raja (North)
[2023/11/21] Section 06: Kapar - Assam Jawa
[2026/? ] Section 07: Assam Jawa - Tanjung Karang
[2019/05/31] Section 08: Hutan Melintang - Teluk Intan
[2019/09/23] Section 09/10: Kampung Lekir - Beruas
[2024/03/12] Section 11/12: Beruas - Changkat Jering
Update [@2026-03-10]:
[2024/08/30] Section 01: Banting - SKVE
[2025/01/22] Section 02: SKVE - KESAS
[2026/? ] Section 03: KESAS - Federal Highway Route 2 (96%)
[2026/03/xx] Section 04: Federal Highway Route 2 - Bandar Bukit Raja (North)
[2019/12/10] Section 05: NNKSB (Shahpadu Highway) - Bandar Bukit Raja (North)
[2023/11/21] Section 06: Kapar - Assam Jawa
[2026/? ] Section 07: Assam Jawa - Tanjung Karang (84%)
[2019/05/31] Section 08: Hutan Melintang - Teluk Intan
[2019/09/23] Section 09/10: Kampung Lekir - Beruas
[2024/03/12] Section 11/12: Beruas - Changkat Jering
Related News:
- 230km Southern WCE Feasibility Study To Conclude By Dec
- WCE targets completion of West Coast Expressway by FY2027
- Feasibility Study For Southern WCE To Be Completed Mid-December | BERNAMA
- WCE project: Melaka set to have six new toll plazas | The Star
- Sinar Harian | Seksyen 4 berpotensi dibuka awal